




May 20, 2006 mock-up Rm. ceiling status
Contractor : DONG DO
Location : Unit 13, Level 6
Sbj : Ceiling panel installation
Saturday May 20, 2006 - 11:21am (ICT) Permanent Link 0 Comments
SWA design review on May 16, 2006
A. Conforming the opening at grid line 2-C level +76.250 ( Ref. Elevation E dwg TD-A406 )
B. Door of Mach. Rm at grid line 2-B level +78.600 : Details missied ( Ref. Elevation E dwg TD-A406 )
C. Opening for Lift equipment installation is too small ( Ref. Section R dwg TD-A424 )
D.Roof of Mach. Rm level +80.950 : Details missied, slope directions? ( Ref. Elevation E dwg TD-A406 )
E. Kitchen level 21 : door and window details missed ( Ref. Lift Hall Plan dwg TD-A406 )
F. Kitchen level 21 : Hosting hook on bottom of the slab details/ request for information ( Ref. Lift Hall Plan dwg TD-A406 )
G. Lift lobby level 21 : Opening on the floor/ dimension and top details conforming ( Ref. Lift Hall Plan dwg TD-A406 )
Tuesday May 16, 2006 - 09:56am (ICT) Permanent Link 0 Comments
Mock-up Rm ceiling status on May 15, 2006
Contractor : COTECLAND
Location : Rest Rm. Ceiling Unit 14, Level 6
Sbj : Floor Holes on Level 7 slab with no waterproof works
Monday May 15, 2006 - 03:42pm (ICT) Permanent Link 0 Comments
Mock-up patition status on May 15, 2006
Contractor : DONG DO
Location : Unit No.13
Monday May 15, 2006 - 01:34pm (ICT) Permanent Link 0 Comments
Mock-up Ceiling status on May 15, 2006
Contractor : DONG DO
Location : Unit No.14
Monday May 15, 2006 - 01:29pm (ICT) Permanent Link 0 Comments
Contractor : DONG DO
Location : Unit 13, Level 6
Sbj : Ceiling panel installation
Saturday May 20, 2006 - 11:21am (ICT) Permanent Link 0 Comments
SWA design review on May 16, 2006
A. Conforming the opening at grid line 2-C level +76.250 ( Ref. Elevation E dwg TD-A406 )
B. Door of Mach. Rm at grid line 2-B level +78.600 : Details missied ( Ref. Elevation E dwg TD-A406 )
C. Opening for Lift equipment installation is too small ( Ref. Section R dwg TD-A424 )
D.Roof of Mach. Rm level +80.950 : Details missied, slope directions? ( Ref. Elevation E dwg TD-A406 )
E. Kitchen level 21 : door and window details missed ( Ref. Lift Hall Plan dwg TD-A406 )
F. Kitchen level 21 : Hosting hook on bottom of the slab details/ request for information ( Ref. Lift Hall Plan dwg TD-A406 )
G. Lift lobby level 21 : Opening on the floor/ dimension and top details conforming ( Ref. Lift Hall Plan dwg TD-A406 )
Tuesday May 16, 2006 - 09:56am (ICT) Permanent Link 0 Comments
Mock-up Rm ceiling status on May 15, 2006
Contractor : COTECLAND
Location : Rest Rm. Ceiling Unit 14, Level 6
Sbj : Floor Holes on Level 7 slab with no waterproof works
Monday May 15, 2006 - 03:42pm (ICT) Permanent Link 0 Comments
Mock-up patition status on May 15, 2006
Contractor : DONG DO
Location : Unit No.13
Monday May 15, 2006 - 01:34pm (ICT) Permanent Link 0 Comments
Mock-up Ceiling status on May 15, 2006
Contractor : DONG DO
Location : Unit No.14
Monday May 15, 2006 - 01:29pm (ICT) Permanent Link 0 Comments
Không có nhận xét nào:
Đăng nhận xét