June 17, 2006 mock-up rm. status
















June 17, 2006 mock-up rm. status

Contractor : WSW, AA decor Sbj : Unit 13, bed rm., W20->W23-flooring works
Saturday June 17, 2006 - 12:20pm (ICT) Permanent Link 0 Comments
June 17, 2006 mock-up rm. status

Contractor : AA decor, Dong Do, Sophy
Sbj : Unit 13, wall, ceiling, tiling, door works
Saturday June 17, 2006 - 12:14pm (ICT) Permanent Link 0 Comments
June 17, 2006 mock-up rm. status

Contractor : AA decor
Sbj : Unit 13, toilet, tiling works
Saturday June 17, 2006 - 12:12pm (ICT) Permanent Link 0 Comments
June 17, 2006 mock-up rm. status

Contractor : Cotecland
Sbj : Unit 14, Mech. rm., tiling works
Saturday June 17, 2006 - 12:09pm (ICT) Permanent Link 0 Comments
June 17, 2006 mock-up rm. status

Contractor : AA decor
Sbj : Unit 14, timber floor installation works