May 24, 2006 Mock-up Rm. status











May 24, 2006 Mock-up Rm. status

Contractor : AA Decor
Location : Unit 13, Level 6
Sbj : Floor screeding status
Wednesday May 24, 2006 - 08:54am (ICT) Permanent Link 0 Comments
WSW shop-drawings status on 20 May 2006

Attn : Mr. COLETO
Sbj : W32 shopdwgs status
Date : 20 May 2006
_______________________________________________
1. Notes in the shop-drawing are too small. WSW must do this in in English.
2. All the detail must be shown in the right scale : 1/5 or same as exist. design dwgs (SWA)
3. All the detail must be suitable to exist. design dwgs (SWA). Pls. see dwgs TD-A500 ( curtain Wall Detail from level 19 to level 22), TD-A523 (section 14, section 15):
+ W32 Connection details level 21 is not suitable to slab structure: The border line of level 21 slab moved out .
+ W32 Connection details level 20 : Add more bolts on the bottom of the slab follow "detail 21-A523" in SWA design.
+ W32 Connection details level 19 : Add more Alum. sheet flashing on the bottom of W32 frame follow "detail 21-A523" in SWA design.
Prepaeed by :


Huynh Dang Binh


Saturday May 20, 2006 - 02:15pm (ICT) Permanent Link 0 Comments
May 20, 2006 Mock-up Rm. ceiling/ M&E works status

Contractor : PME
Location : Unit 13, Level 6
Sbj: PME is doing M&E works on the ceiling
Saturday May 20, 2006 - 11:43am (ICT) Permanent Link 0 Comments
May 20, 2006 Mock-up Rm.Rendering works status

Contractor : COTECLAND
Location : Unit 13, Level 6
Sbj : Redo Plastering(finish coat)
Saturday May 20, 2006 - 11:27am (ICT) Permanent Link 0 Comments
May 20, 2006 mock-up Rm.ceiling status

Contractor : DONG DO
Location : Unit 14, Level 6
Sbj : Ceiling panel installation
Saturday May 20, 2006 - 11:23am (ICT) Permanent Link 0 Comments